'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months
Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
What is the exchange rate of which foreign currency on Wednesday?
Kathmandu. Nepal Rastra Bank has determined the foreign currency exchange rate for Wednesday. The value of the US dollar has increased according to the fixed exchange rate. The buying rate of one US dollar is 149 rupees 31 paisa and the selling ra...
The American dollar kept a high point record today, how much is one dollar Nepalese rupee?
Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the fixed rate, the value of the US dollar has risen and reached its highest point so far. According to the exchange rate, the buying rate of...
Petrol and diesel prices stable
Kathmandu. Nepal Oil Corporation has decided to continue the retail sale price of petroleum products. Despite receiving the new purchase price from Indian Oil Corporation (IOC), the Board of Directors' meeting held on Monday decided not to change...
'Stalls' including public library closed after non-payment of rent
Kathmandu. According to the decision of the Nepal government, stalls that have not paid rent for a long time along with the Kathmandu Valley Public Library at Bhrikutimand have been closed. According to the Ministry of Women, Children, Gender and...
Determining the limit of internal debt for the next financial year
Kathmandu. The National Natural Resources and Finance Commission has determined the limit of internal debt that can be taken by the union, state and local levels for the next fiscal year 2083, 84. Based on macroeconomic conditions, revenue trends,...
New Government Still Relies on Foreign Loans Instead of Collecting Revenue
By Anusa Thapa
Bhaktapur, Nepal — The courts issue orders, but the government fails to implement them. This reality is clearly reflected in the government's inability to collect taxes and revenues despite repeated court directives.
Cou...