'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months
Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
Petrol and diesel prices stable
Kathmandu. Nepal Oil Corporation has decided to continue the retail sale price of petroleum products. Despite receiving the new purchase price from Indian Oil Corporation (IOC), the Board of Directors' meeting held on Monday decided not to change...
NEPSE decreased by eight digits, turnover of more than 2.83 billion
Kathmandu. The NEPSE index, which measures stock turnover in the stock market, is still down today. According to the Nepal Stock Exchange, the NEPSE index fell by 8.50 points and was limited to 2,651.52.
The sensitive index, which measures t...
NEPSE rose by 9.93 points, 7.5 billion shares traded
Kathmandu. On the third trading day of the week, NEPSE index increased by 9.93 points to 2649.30 points. Today, when 1 crore 48 lakh shares of 334 companies were bought and sold, there was a turnover of more than 7 billion 12 crore rupees. Among t...
Driving license will be available within 24 hours from July
Kathmandu. The government has prepared to implement the provision of driver's license within 24 hours of passing the trial from July. According to the Ministry of Physical Infrastructure and Transport, as there are currently about 300,000 licenses...
Increase in the price of petroleum products
Kathmandu. The price of petroleum products has decreased. With the Indian Oil Corporation sending new prices on Sunday, when the Nepal Oil Corporation adjusted the prices, the prices of diesel and kerosene have decreas...
Livelihood raised from goat rearing
Myagdi. Kul Bahadur Pun of Mangala Rural Municipality-2 Hidi has started earning lakhs of rupees annually from the farm he started with two goats four years ago. The 50-year-old has become self-employed and self-sufficient by operating a managed g...