'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months

Main News Image

Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.

"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."

Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.

mediabaaji add

Related News

The NEPSE index fell by a few points

Kathmandu. The NEPSE index, which measures stock trading in the stock market, has fallen by a few points today. According to the Nepal Stock Exchange, the NEPSE index fell by two points and reached 2,649.51.

The snsitive index, which measure...

Instructions not to trade in street boxes

Kathmandu. Triyuga Municipality has requested not to do business in the main streets of Gaighat Bazar, the headquarters of Udaipur. Chief Basant Basnet informed that the municipality has also conducted awareness training for 225 sidewalk traders a...

Janakpur Cigarette Factory in Pakhai to be reopened

Janakpur. The only cigarette factory in the country, Janakpur Cigarette Factory Limited, which was operating 62 years ago, is in the process of reopening. The Janakpur cigarette factory, which was unfortunately closed due to the political environm...

Five construction companies blacklisted, barred from participating in any public procurement

Kathmandu. The Public Procurement Monitoring Office has blacklisted five construction companies. The office issued a notice today and said that the company has been blacklisted.

According to the written submissions from various agencies, acc...

Public transport fares increased

Kathmandu. Public transport fares have increased. After the ministerial decision of Physical Infrastructure and Transport Minister Sunil Lamsal, the Transport Management Department has increased the fare. After the recent increase in the price of...

Normal improvement in NEPSE: 4 billion 400 million turnover with an increase of 7 points

August 4, Kathmandu. There has been a modest increase in NEPSE. On Thursday, NEPSE increased by 7.17 points and stopped at 2629.40 points. Today, 95 lakh 766 shares of 345 companies were traded for 4 billion 40 crore 14 lakh 9 thousand 858 shares....