'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months
Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
Nagadhunga is mostly deserted after the tunneling
Dhading Nagadhunga road, which is always smoky and chaotic with traffic jams, is mostly deserted this year even during Dashain. Nagadhunga-Sisnekhola tunnel, the main gateway to the federal capital Kathmandu from around 68 districts of the country...
Chandragiri Investment Group will issue 'IPO' shares
Kathmandu. Chandragiri Investment Group Limited is going to issue a primary share IPO for ordinary citizens. The company's first general meeting held today passed the proposal to issue the IPO. The authorized capital of the company is Rs 50...
Vijay Laguvitta's FPO will be distributed on Friday
Kathmandu. Preparations have been made to distribute this week to the FPO of Vijay Microfinance Financial Institution. Sales manager NMB Capital is preparing to distribute the FPO on Friday. By the last day, 22 lakh 99 thousand 252 people had appl...
Sopan Pharmaceuticals' IPO issue date change, when will it open now?
Kathmandu. The issue date of the IPO that Sopan Pharmaceuticals is going to issue to the general public has been changed. IPO to be issued from 2nd to 6th Baisakh, 2083 The IPO to be issued will be open from 3rd. The release date has been changed...
Why did those who protested yesterday take a loan today?
Kathmandu. CPN-UML General Secretary Shankar Pokharel has raised questions regarding the current government's duplicitous nature regarding foreign loans. He says that those who criticized foreign loans in the past are now taking large amounts of l...
What is the exchange rate of which foreign currency on Thursday?
Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to Rashtra Bank, the buying rate of one US dollar has been fixed at 145 rupees 22 paisa and the selling rate is 145 rupees 82 paisa. Similarly,...