Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
This is the foreign exchange rate
The Kathmandu. Nepal Rastra Bank has fixed the exchange rate of foreign currency for today. According to the National Bank, the buying rate of US dollar has been fixed at 152 rupees 31 paise and selling rate at 152 rupees 91 paise. The Australian...
What is the exchange rate of which foreign currency on Sunday?
Kathmandu. Nepal Rastra Bank has determined the foreign currency exchange rate for Sunday. According to the fixed exchange rate, the buying rate of one US dollar is 144 rupees 37 paisa and the selling rate is 144 rupee...
Fall in the price of gold and silver, how much is the transaction per tola today?
Kathmandu. There has been a general decline in the price of gold and silver in the Nepalese market on Monday. According to the Federation of Nepal Gold and Silver Dealers, compared to Sunday, gold decreased by Rs 400 per tola on Monday. The federa...
Starting today, financial calculations are being conducted across the country
Kathmandu. From today, the second financial calculation is being conducted across the country. According to the National Statistics Office, the enumerators and necessary supervisors have reached the relevant areas all over the country. According t...
Sopan Pharmaceuticals' IPO issue date change, when will it open now?
Kathmandu. The issue date of the IPO that Sopan Pharmaceuticals is going to issue to the general public has been changed. IPO to be issued from 2nd to 6th Baisakh, 2083 The IPO to be issued will be open from 3rd. The release date has been changed...
NEPSE decreased by 2.25 points, trading at 5.52 billion
Kathmandu. On the first day of the week's trading, the stock market fell by a few points on Monday. According to Nepal Stock Exchange (NEPSE), the NEPSE index decreased by 2.25 points to 2641.58 points.
Out of the 13 sub-groups traded on Mon...