'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months
Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
42.58 points decline in NEPSE, turnover above 14.16 billion
Kathmandu. On the third trading day of the week, NEPSE index decreased by 42.58 points and remained at the point of 2726.51. 14 billion 1671 million shares were traded during the day when 32 million 62 thousand 710 shares of 333 companies were bou...
Foreign currency exchange rate set for today
Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the National Bank, the buying rate of one US dollar has been fixed at 150 rupees 87 paisa and the selling rate is 151 rupees 47 paisa. The bu...
Sanima Middle Tamor Hydropower's dividend declaration, general meeting call
Kathmandu. Sanima Middle Tamor Hydropower Limited is going to distribute 5.263 percent cash dividend to the shareholders. The meeting of the board of directors of the company has proposed to distribute the dividend from the distributable accumulat...
Construction of Kohalpur-Surkhet 132 KV transmission line has been completed
Kathmandu. Nepal Electricity Authority has completed the construction of Kohalpur-Surkhet 132 KV transmission line. The construction of the Kohalpur-Surkhet section has been completed under the Kohalpur-Surkhet-Dailekh 132 KV transmission line pro...
Extension of application deadline for companies dealing in real estate
Kathmandu. The Department of Land Management and Records has extended the deadline for applications for firms, companies or organizations that want to get a license to deal with real estate. The department has extended...
NEPSE rose, the index to 2,597 points as share prices of 121 companies increased
Kathmandu. On Thursday, the last trading day of the current financial year, the Nepal Stock Exchange NEPSE index has closed with an increase of normal points. The market, which has been fluctuating throughout the day, improved at the end of tradin...