Muglin -Malekhu road upgradation work started
Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.
According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.
According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.
This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.
Express
Related News
Kalinchok Hydropower will issue IPO from 13th of February
Kathmandu. Kalinchok Hydropower Limited is going to issue IPO from 13th of February. The company is about to issue an IPO for the local residents of the project-affected areas and Nepalis working abroad.
The company got permission to issue 1...
Kalanga Hydro's IPO collects 2 billion rupees, how many applied?
Kathmandu. 2 billion 25 lakh 29 thousand rupees have been collected in the IPO of Kalanga Hydro Limited. According to CDS, 17 lakh 79 thousand 593 people have applied for 2 crore 25 thousand 290 shares till 5 pm today on 10th May. The company has...
After raising the discretionary price of Khasi meat, the government's interest, preparation to fix the maximum price limit
Kathmandu. After increasing the price of beef in the market, the government has started preparing to set a price limit. The Ministry of Agriculture, Forestry and Environment has made such preparations after receiving public complaints that the pri...
6.20 billion turnover, a normal point growth in NEPSE
Kathmandu. On the third trading day of the week, NEPSE index increased by 1.52 points to 2641.43. During the day, 125 million 4970 shares of 320 companies were bought and sold, and 6 billion 209.4 million shares were traded.
Today, while the...
Government's priority in building high capacity transmission lines
Kathmandu. The government has announced a deadline for constructing high-capacity transmission lines to deliver the produced electricity to the major load centers, sell and distribute excess electricity at the regional and sub-regional levels.
...Eastern tea industries closed after India's blockade, 60,000 jobs in crisis
Kathmandu. After India imposed an unannounced ban on Nepali tea exports, the tea industries of Elam and Jhapa have started to close down. 56 industries in Elam have already been closed, while more than 30 industries and about two dozen tea gardens...