Muglin -Malekhu road upgradation work started

Main News Image

Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.

According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.

According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.

This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.

mediabaaji add

Related News

What is the foreign currency exchange rate on Sunday?

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the Rashtra Bank, the buying rate of one US dollar has been fixed at 141 rupees 70 paisa and the selling rate ha...

Contracts of 25 construction companies that did not work according to the contract were terminated

Kathmandu. The government has terminated the contract with 25 construction companies that did not complete the construction as per the contract. Federal Road Supervision and Monitoring Office Kathmandu under the Road D...

NEPSE fell by 10.25 points, trading fell to 8 billion 61 crores

Kathmandu. On the third trading day of the week, NEPSE index decreased by 10.25 points to 2662.14. Today, 21.17 million 15 thousand 868 shares of 324 companies were bought and sold, and 8.61 billion 64 million shares were traded. Today, while the...

What is the exchange rate of which foreign currency on Tuesday?

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the exchange rate set for today, the value of the US dollar has increased. According to the fixed exchange rate, the buying rate of one US do...

Three billion worth of electric vehicles entered in 9 months through the Birganj border crossing

Parsa. In the nine months of the current financial year, electric vehicles worth 2.98 billion rupees have been imported through the Birganj route. Compared to the same period of the last financial year, electric vehicles have been imported by 102...

What is the foreign currency exchange rate on Wednesday?

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to Rashtra Bank, the buying rate of one US dollar has been fixed at 140 rupees 93 paisa and the selling rate is 141 rupees 53 paisa. Similarly,...