Muglin -Malekhu road upgradation work started

Main News Image

Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.

According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.

According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.

This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.

mediabaaji add

Related News

Nepal Life's 'Business Excellence Conference' completed, more than 13 billion first insurance fees collected last year

Kathmandu. Nepal Life Insurance, the most reliable life insurance company of Nepal, has successfully completed the two-day 'Business Excellence Conference'. More than 280 employees of sales and marketing departments from all over the country parti...

From today, cylinder gas in the market: Price fixed at 2 thousand 60 rupees per cylinder

Kathmandu. Addressing the discomfort of cooking gas LP gas seen in the market and the demand of consumers, Nepal Oil Corporation is going to start the sale and distribution of full weight cylinders of gas across the country from Wednesday. The cor...

Minister Ghising said on the monitoring of Mahakali irrigation, talks are being held with India about releasing water

Kathmandu. Energy, Water Resources and Irrigation, Physical Infrastructure and Transport and Urban Development Minister Kulman Ghising has inspected the Tanakpur Barrage at Brahmadev in Kanchanpur. While inspecting the...

Gold prices modestly rise, silver sets new record

Kathmandu. On Wednesday, the price of gold in the Nepali market has increased. Today, the price of gold has increased by Rs 700 per tola. According to the Federation of Nepal Gold and Silver Traders, the price of gold...

11 km Nagadhunga-Malekhu section under Prithvi Highway is blacked out

Chitwan. Under Prithvi Highway, 11 km Nagdhunga Malekhu section has been blacked out. Last year eight kilometers were blacked, this year three more kilometers were blacked. According to Vijay Darai, Engineer of Nagadhunga Muglin Road Project, unde...

High increase in gold prices, how much per tola on Friday?

Kathmandu. The price of gold has increased in Nepali market today. Gold tola increased by 5 thousand 300 rupees. According to the Nepal Gold and Silver Traders Federation, gold is being bought and sold at 292,000 rupees per tola today.

On th...