Muglin -Malekhu road upgradation work started

Main News Image

Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.

According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.

According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.

This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.

mediabaaji add

Related News

Kalinchok Hydropower will issue IPO from 13th of February

Kathmandu. Kalinchok Hydropower Limited is going to issue IPO from 13th of February. The company is about to issue an IPO for the local residents of the project-affected areas and Nepalis working abroad.

The company got permission to issue 1...

Trial of Tamghas-Burtibang 132 KV transmission line started

Kathmandu. The testing of the 132 kV double circuit transmission line constructed by the Nepal Electricity Authority from Gulmi headquarters Tamghas to Burtibang has been started from today. The line built under Burtibang-Paudiamrai-Tamghas-Sandhi...

What is the exchange rate of foreign currency on Tuesday?

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to Rashtra Bank, the buying rate of one US dollar has been fixed at 140 rupees 90 paisa and the selling rate is 141...

Nepal gave three and a half million US dollars for the reconstruction of two religious places in Myanmar

Kathmandu. The Government of Nepal has provided 350,000 US dollars to the Government of Myanmar for the reconstruction of two religious heritage sites in Myanmar that were damaged by the powerful earthquake of last March.

Ambassador of Nepal...

What is the exchange rate of which foreign currency for Tuesday?

Kathmandu. Nepal Rastra Bank has determined the foreign currency exchange rate for Tuesday. According to Rashtra Bank, the buying rate of one US dollar has been fixed at 142 rupees 48 paisa and the selling rate is 143...

22 helicopters are deployed for rescue, the government is gathering international support

Kathmandu. Finance Minister Swarnim Wagle has said that during the national crisis, all political parties and parties should come together and move forward for a solution. 

Speaking to the media after the all-party meeting organized by...