Muglin -Malekhu road upgradation work started

Main News Image

Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.

According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.

According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.

This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.

mediabaaji add

Related News

National Life's CEO Club member honor program completed

Kathmandu. National Life Insurance Company Ltd. has completed the CEO Club member honoring program for the agents of Koshi region at Hotel The Kingsbury located in Birtamod under the chairmanship of the chief executive officer of the company. In t...

About 52 crore relief will be provided to the farmers within a week

Kathmandu. The Department of Animal Services has prepared to provide Rs 52 crore to farmers within a week as compensation for birds and goods destroyed during disease control in 11 districts affected by bird flu. The department has prepared to pro...

Gold price increased on Friday, how much per tola?

Kathmandu. The price of gold has increased in Nepali market today. Gold tola has gone up by 900 rupees. According to the Nepal Gold and Silver Traders Federation, gold is being bought and sold at 296,900 rupees per tola today. Today, the price of...

What is the new exchange rate for foreign currencies, US dollars and pounds?

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the new rate issued by the Central Bank, today the buying rate of one US dollar is 154 rupees 02 paisa and the selling rate is 154 rupees 62...

Gold prices continue to set new records, silver is also at an all-time high

Kathmandu. The price of gold and silver in the Nepali market is constantly increasing. Today the price of gold has increased by 1 thousand 800 rupees. According to the Federation of Nepal Gold and Silver Dealers, the...

Sabhakhola 'B' hydropower project tunnel 'break through'

Kathmandu. The tunnel of the under-construction Sabhakhola 'B' hydropower project in Sabhapokhari Rural Municipality of Sankhuwasabha has been breached. The main tunnel of the 21.5 MW Sabha Khola project, which is under construction using Sabha Kh...