Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.
According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.
According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.
This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.
Express
Related News
Government's relief package: Rasuwa flood victims will get up to 50% advance insurance claim payment
Kathmandu. The government has decided to provide advance payment to the insured affected by the Rasuwa flood based on the preliminary assessment of insurance claims. This arrangement has been made through the 'Rasuwa flood recovery package' announ...
Iran turning problems into opportunities, making billions of dollars under the guise of war
Kathmandu. Iran has turned the war with the US and Israel into an opportunity. The U.S. targeted military bases near the island of Kharg Iran, but did not directly target an oil terminal for fear of a global oil crisis. Taking advantage of this, I...
Janakpur Cigarette Factory in Pakhai to be reopened
Janakpur. The only cigarette factory in the country, Janakpur Cigarette Factory Limited, which was operating 62 years ago, is in the process of reopening. The Janakpur cigarette factory, which was unfortunately closed due to the political environm...
There is no possibility of immediate major flood in Bhotekoshi, department request not to follow rumours
Kathmandu. Amidst fears that Himtal in Rasuwa and Nuwakot districts may explode and flood the Bhotekoshi River, the Department of Water and Meteorology has made it clear that there is no possibility of such a major flood immediately. Due to the sp...
The IPO of Suryakund Hydro Electric will be distributed on Tuesday
Kathmandu. The IPO issued by Suryakunda Hydro Electric Limited for Nepalis working abroad will be distributed on Tuesday. Sales Manager Kumari Capital has informed that a program for allotment of shares has been scheduled at the capital's office a...
The price of gold decreased by 20 thousand rupees
Kathmandu. The price of gold and silver has decreased in the local market today. Compared to Thursday, the price of both metals has decreased. According to the Nepal Gold and Silver Traders Association, today the price of one tola of gold is 318 t...