Muglin -Malekhu road upgradation work started
Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.
According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.
According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.
This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.
Express
Related News
Fall in the price of gold, now how much per tola?
Kathmandu. The price of gold has decreased in Nepali market today. Gold tola has fallen by one thousand rupees. According to the Nepal Gold and Silver Traders Federation, gold is being traded at 283,200 rupees per tola today. The price of 10 grams...
National Life's CEO Club member honor program completed
Kathmandu. National Life Insurance Company Ltd. has completed the CEO Club member honoring program for the agents of Koshi region at Hotel The Kingsbury located in Birtamod under the chairmanship of the chief executive officer of the company. In t...
Saturday's exchange rate, the value of the dollar and the currencies of the Gulf countries
Kathmandu. Nepal Rastra Bank has determined the official exchange rate of foreign currencies for Saturday. According to the Central Bank, today the buying rate of one US dollar has remained at 150 rupees 74 paisa and the selling rate has remained...
Gold has fallen from its highest price, while silver has hit a new record
Kathmandu. The price of gold has decreased from its highest value so far. Gold today fell by Rs 600 per tola. According to the Nepal Gold and Silver Traders Federation, today the price of gold is being bought and sold at 270,000 rupees per tola. O...
Kalanga Hydro's IPO collects 2 billion rupees, how many applied?
Kathmandu. 2 billion 25 lakh 29 thousand rupees have been collected in the IPO of Kalanga Hydro Limited. According to CDS, 17 lakh 79 thousand 593 people have applied for 2 crore 25 thousand 290 shares till 5 pm today on 10th May. The company has...
6 percent of Bagmati budget expenditure in three months
Kathmandu. In the first three months of the current fiscal year 2082-83, the Bagmati state government has spent only about 6.19 percent of the total budget. According to Suraj Paudel, information officer of the Ministr...