Electricity generation started from Setikhola project

Main News Image

Kaski. Setikhola hydropower project of 22 megawatt capacity, completed in Pokhara Metropolitan City-33 of Kaski, has started generating electricity. The project promoted by Seti Khola Hydropower Limited started in December 2078.

After the inspection and testing of the project by the technical team of the Nepal Electricity Authority, the produced electricity has started to flow in the national transmission system as a test, according to Deepak Baral, the director of the promoter company.

According to him, initially 15 days will be in the project trial period. After that, regular commercial production will begin. During that period, the electricity produced will be transferred to the Nepal Electricity Authority's system, while technical testing of the project and equipment will be conducted.

mediabaaji add

Related News

Stock market fell sharply, turnover fell to 9 billion

Kathmandu. The stock market fell on Thursday. Today, the NEPSE index decreased by 33.83 points to close at 2,833.03 points, which is a decrease of 1.18 percent. Today, a total of 207 million 43 thousand 884 shares were bought and sold, and the tra...

Heavy fall in the price of gold, now how much per tola?

Kathmandu. The price of gold in the Nepalese market has fallen drastically today. Gold fell by Rs 5,400 per tola in one day. According to the Nepal Gold and Silver Traders Federation, gold is being traded at 32,300 rupees per tola today.

On...

The price of the US dollar exceeded 152 rupees, how many other currencies?

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the fixed exchange rate, the buying rate of one US dollar is 151 rupees 56 paisa and the selling rate is 152 rupees 16 paisa. Similarly, the...

Certificate for those who contribute more than 10,000 to the reconstruction fund

Kathmandu. The government is going to give certificates to those who contributed more than 10,000 to the physical infrastructure reconstruction fund established for the reconstruction of the damage caused during the Genji movement of 23 and 24 Aug...

Extension of application deadline for companies dealing in real estate

Kathmandu. The Department of Land Management and Records has extended the deadline for applications for firms, companies or organizations that want to get a license to deal with real estate. The department has extended...

Illegal goods worth 3.5 million seized in Rasuwa in 9 months

Rasuwa Illegal imported materials worth Rs 351 lakh 76 thousand 420 have been seized in Rasuwa from July to March of the current financial year. According to the Rasuwa Customs Office, as part of the revenue leakage control campaign, the goods of...