Kathmandu. Tundi Power Company has simultaneously constructed two hydropower projects on the Rahughat River that flows through Raghuganga Rural Municipality of Myagdi. Ghuganga Rural Municipality-4, 7 and 8 Ward No. 4, 7 and 8 of the two projects of 84 MW capacity are connected to the electricity central system.
Pushpa Dangi, the company manager of Tundi Power, informed that after the testing of the project of the nature of 'Run of the River', the commercial production has started. "Chimkhola-Rahughat-Mangale with a capacity of 35.5 megawatts promoted by Tundi Power and Upper Rahughat hydropower project with a capacity of 48.5 megawatts as a 'cascade' have been put into operation", he said, "Chimkhola-Rahughat-Mangale has started commercial production since last July 20. It is in the stage of commercial production.

Manager Dangi said that the projects built during four years can be operated at full capacity according to the available water resources. According to him, the estimated cost of both projects is 13 billion. Resident engineer Prakash Timilsina said that the electricity generated from these projects is temporarily connected to the national system from the 'switchyard' of the Rahughat hydropower project in Raghuganga Rural Municipality-3 Tilkenichaur. According to him, 39 towers have been constructed from Chimkhola to Rahughat.

A 110-meter long, eight-meter high and 30-meter wide water-cooling pond has been constructed near the dam in Raghuganga Rural Municipality-8 Bandi of Chimkhola-Rahughat-Mangale. A 950-meter penstock pipeline has been installed to drop the water brought from the dam through a five-kilometer, 300-meter long tunnel to the power plant at Bagar in Raghuganga-7 Chimkhola. Engineer Timilsina informed that the height of the outlet of the tunnel from electricity is 360 meters.

Electricity has been generated from Chimkhola-Mangale-Rahughat by using water from Chimkhola-Mangale-Rahughat and Bagarkhola of Chimkhola. Raghuganga Rural Municipality-4 The tunnel of Upper Rahughat, where the power house is located at the foot of Dagnam, is 4,900 meters long. A 680 meter long penstock pipeline has been connected from the outlet to the power house.

mediabaaji add

Related News

Now 100 rupee notes will be available from ATMs

Kathmandu. Nepal Rastra Bank has asked banks and financial institutions to make arrangements to distribute Rs 100 and Rs 100 notes along with Rs 1,000 and Rs 500 notes from the ATMs of banks and financial institutions.

The National Bank thro...

Prachanda-Madhav in Pokhara warned by businessmen not to hold street meetings

Pokhara. Businessmen of Pokhara have protested saying that holding meetings on the streets will affect their business. Nepali Communist Party (NCP) protested at Ekta Synagogue that the Nepali Communist Party (NCP) will...

U.S. to provide more than $3 million in flood relief

The Kathmandu. The U.S. government has announced more than $3.6 million in additional humanitarian assistance for Nepal's flood victims. In a press statement issued on Saturday, the US State Department said that the US will provide more than $3.6...

More liquidity in banking system, Rashtra Bank pulling 50 billion today

Kathmandu. Nepal Rastra Bank is going to withdraw 50 billion rupees from the banking system today, January 28th. To manage excess liquidity, the central bank is using deposit collection tools to withdraw money from the banking system. 

...

Construction of Kohalpur-Surkhet 132 KV transmission line has been completed

Kathmandu. Nepal Electricity Authority has completed the construction of Kohalpur-Surkhet 132 KV transmission line. The construction of the Kohalpur-Surkhet section has been completed under the Kohalpur-Surkhet-Dailekh 132 KV transmission line pro...

The US dollar and euro rose, as did other currencies

Kathmandu. Nepal Rastra Bank has announced the official exchange rate of foreign currency for Thursday. According to the new rate set by the National Bank, today the buying rate of one US dollar is 151 rupees 46 paisa and the selling rate is 152 r...