Construction of 27 km road of Naubise-Malekhu section completed

Main News Image

Kathmandu. Under the Nagadhunga-Mugling road expansion project, the construction work of Naubise-Malekhu section has gained momentum. In this second section, which has a total length of 43 km, a total of 27 km of road construction has been completed with 25 km of asphalt and 2 km of sloping rigid pavement.

According to Keshav Ojha, head of planning of Nagadhunga-Mugling road project eastern section, the overall physical progress of this section has reached 60 percent. Although the project aims to achieve 75 percent physical progress in the current financial year, due to the lack of bitumen in the international market, some obstacles were created in achieving the goal. He informed that although there was a problem in the supply of bitumen due to the tension in the Middle East, the supply has been eased after the facilitation of the Ministry of Infrastructure Development and the work has resumed speed.

mediabaaji add

Related News

Rescue of a person trapped in the middle of Mahakali river

Kathmandu. The police rescued a person who was stuck in the middle of the Mahakali river. At 7:30 this morning, police rescued 52-year-old Umesh Chaulagai of Kavrepalanchok Chaurideurali-6 Laharetol, who was stranded on an island in the middle of...

Dedicated and Trunkline Disputes Resolved: Agreed to connect lines on bail

Kathmandu. In the high-level discussion, a compromise proposal has been agreed on in the dedicated and trunk line dispute. A middle-ground proposal acceptable to both sides has been put forward from the discussion held...

14 injured when truck and bus collided

Kathmandu. 14 people were injured when a truck loaded with rice and a passenger bus collided in Makwanpur on Thursday. The accident occurred when a rice load truck No. BAPR 06001 B 0415 and a passenger bus No. BPA 101001 B 4768 coming from the opp...

38 people are believed to be trapped in the Upper Trishuli 3 'A' Tunnel: The mouth of the tunnel was opened by blasting

The Kathmandu. As many as 38 technicians and workers are believed to be trapped inside the tunnel tunnel of the 60-megawatt Upper Trishuli 3A hydropower project due to the severe floods in the Bhotekosi and Trishuli rivers on Wednesday.

Con...

Passenger sumo accident in Ramechhap, how is the condition of passengers?

Ramechhap. A passenger sumo met with an accident on Monday morning in Khandadevi rural municipality-6 Makadum of Ramechhap. BAPR 08 (001 J 0224) carrying passengers from Khandadevi 7 Timu towards Kathmandu has met with an accident. A total of 6 pe...

12 sick contracts of irrigation were broken, the process of breaking 40 more road contracts started

Kathmandu. 12 sick contracts for irrigation, which have been stalled for years due to lack of contract agreement, have been broken. 12 patient contracts under former People's Embankment Program Field Office No. 2 Jaleshwar Mahottari have been brok...