'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months
Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
New records are constantly being made in the price of gold and silver, how much has it reached today?
Kathmandu. The price of gold and silver has increased in the Nepalese market on Sunday. Today, the price of gold has increased by Rs 1,300 per tola. According to the Nepal Gold and Silver Dealers Federation, 270 thousand 600 rupees have been fixed...
Kathmandu-Dubai flight will be opened from today
Kathmandu. Fly Dubai will operate flights on Dubai-Kathmandu-Dubai route tonight. According to the Tribhuvan International Airport office, nine countries in the region stopped flights on the air route due to the tension created after the joint mil...
An increase of 4.59 points in NEPSE, the turnover is 4.9 billion
Kathmandu. On the fifth or last trading day of the week, NEPSE index increased by 4.59 points to 2640.54. During the day, 104 million 31 thousand 760 shares of 328 companies were bought and sold, resulting in a turnover of 4 billion 908 million sh...
After the opening of Tatopani and Rasuwagadhi, Korlanaka's business declined
Mustang. After Tatopani and Rasuwagadhi checkpoints came into operation, the import-export trade from Nepal-China North Korlana located in Mustang has decreased. According to the Mustang Customs Office, there are currently very few cargo container...
5 lakh more income in one year from flower farming
Walling. Tulsiram Bhandari of Chapakot Municipality-1 Chowghera in Syangja has been earning five lakhs more in a year from commercial flower farming. He, who is also a former teacher, has been cultivating flowers targeting Dasain and Tihar.
<...The capital market increased by 45 percent: shine in the banking and financial sector!
Kathmandu. The stock market continues to fluctuate continuously. Although the market fell by a few points on Tuesday, there was an improvement on Wednesday. Although it has increased today, the current ups and downs are considered to be the effect...