'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months
Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.
"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."
Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.
Express
Related News
BP highway reconstruction is accelerated, 3.2 km road will be constructed through JICA for 2.6 billion
Ramechhap. The remaining road section of the Kavre-Sindhuli section from Piple in Kavre to Barkhekhola in Sindhuli will be constructed in two lanes with the support of Japan International Cooperation Agency (JICA).
Suman Yogesh, Head of Road...
NADA Auto Show 2026 begins, special priority for 'Made in Nepal' vehicles
Kathmandu. While the vehicle market is expanding in Nepal, NADA Auto Show 2026 has started at Bhrikutimandap in Kathmandu, giving priority to domestically produced and assembled vehicles and automobile materials.
Vice President Ramsahay Yada...
Why did those who protested yesterday take a loan today?
Kathmandu. CPN-UML General Secretary Shankar Pokharel has raised questions regarding the current government's duplicitous nature regarding foreign loans. He says that those who criticized foreign loans in the past are now taking large amounts of l...
The government is issuing 10 billion 9-year 'Development Bond 2091'
Kathmandu. The government is going to issue development bonds worth 10 billion rupees. The Public Debt Management Office under the Ministry of Finance is going to sell 9-year bonds named 'Development Bond 2091'.
The office issued a not...
The budget is meant to feed the ambitious and wealthy, the target is not met: Former Finance Minister Mahat
Kathmandu. Former finance minister and Nepali Congress leader Dr. Prakasharan Mahat has commented that the budget for the next financial year 2083-84 brought by the government is very ambitious and it has taken a policy to feed the rich class rath...
After a week, the stock market fell, the turnover did not increase
Kathmandu. The stock market, which has increased for 6 consecutive trading days, fell by 13.95 points on Wednesday and the NEPSE index fell to 2,712 points. The transaction amount has also decreased from 6.67 billion rupees the previous day to 5.1...