'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months

Main News Image

Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.

"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."

Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.

mediabaaji add

Related News

What is the exchange rate of which foreign currency on Friday?

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the fixed exchange rate for today, the buying rate of one US dollar is 143 rupees 65 paisa and the selling rate is 144 rupees 25 paisa.

Nepal Life's 'Business Excellence Conference' completed, more than 13 billion first insurance fees collected last year

Kathmandu. Nepal Life Insurance, the most reliable life insurance company of Nepal, has successfully completed the two-day 'Business Excellence Conference'. More than 280 employees of sales and marketing departments from all over the country parti...

Nagadhunga-Sisne river tunnel from today mandatory toll!

Kathmandu. Toll fee will be charged from today for using Nagadhunga-Sisne river tunnel. Separate toll charges have been set for cars, buses, trucks and lorries for using the tunnel according to the size and direction of the vehicle. The government...

IPO distribution of Ridge Energy completed, 1 lakh 18 thousand people got shares

Kathmandu. Ridge Line Energy Limited has completed the IPO process issued to the general public. Sales manager Prabhu Capital completed the allotment this morning. IPO of the company 118 thousand 26 people have acquired 11 lakh 80 thousand 260 sha...

Foreign Currency Exchange Rates: What are the rates for Dollars, Euros and Pounds?

Kathmandu. Nepal Rastra Bank has determined the official exchange rate of foreign currency for today. According to the Central Bank, today the buying rate of Indian rupees 100 is fixed at 160 rupees and the selling rate of 160 rupees is 15 paise....

Today, NEPSE decreased by a normal number, the turnover fell to 7 billion 49 crores

Kathmandu. On the fourth trading day of the week, the NEPSE index decreased by 1.64 points to 2681.50. During the day, 1 crore 66 lakh 82 thousand 626 shares of 326 companies were bought and sold, and 7 billion 49 crore 97 lakh shares were traded....