'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months

Main News Image

Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.

"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."

Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.

mediabaaji add

Related News

Preparing to introduce monetary policy on July 1, the National Bank Act is being amended

Kathmandu. The government is going to announce the monetary policy from the next financial year on July 1. Necessary legal preparations have been made for that. This agreement was reached during the regular discussion on the bill made to amend the...

What is the exchange rate of which foreign currency on Sunday?

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for Sunday. According to the determined exchange rate, the buying rate of one US dollar is 147 rupees 64 paisa and the selling rate is 148 rupees 24 paisa. Similarly...

Preparation for operation on Nagadhunga Tunnel from July

Kathmandu. Necessary preparations have been started to bring the vehicles into operation from the month of July through the Nagadhunga-Naubise tunnel. It is expected that with the launch of Nepal's long-awaited tunnel project, traffic on the Naubi...

NEPSE rose by 9.93 points, 7.5 billion shares traded

Kathmandu. On the third trading day of the week, NEPSE index increased by 9.93 points to 2649.30 points. Today, when 1 crore 48 lakh shares of 334 companies were bought and sold, there was a turnover of more than 7 billion 12 crore rupees. Among t...

An increase of 27.19 points in NEPSE, turnover above 11.58 billion

Kathmandu. On the fifth trading day of the week, the NEPSE index increased by 27.19 points to 2708.70. Today, 35.55 million 74 thousand 627 shares of 326 companies were bought and sold, and 11.58 billion 28 million shares were traded. Today, while...

The stock market closed down with normal numbers, "positive circuit" in 4

Kathmandu. On the first trading day of the week, there was a general decline in the stock market. NEPSE index decreased by 4.18 points to 2833.60 points. Although 20 million more shares were traded, the turnover was 8 billion 66 million rupees.&nb...