November 13, 2026, Friday
English

'Upper Myagdi' Hydropower Project: 50% physical progress in 13 months

Main News Image

Myagdi. In the 13 months since the construction of the under construction 'Upper Myagdi' hydropower project in Dhawalagiri Rural Municipality of Myagdi, 50% physical progress has been achieved. The 46.25 MW capacity project promoted by Hydro Empire Limited has accelerated the construction of dams, tunnels, power houses, transmission lines, hydro and electromechanical projects with the goal of starting electricity generation within the month of March 2083. Ramesh Subedi, the head of the project, informed that the construction of the project, which started in March 2081, has achieved 50 percent physical progress.

"We have progressed the work according to the action plan to complete the underground structure including the tunnel within the next eight months", he said, "The civil contractor is doing the work of the tunnel, dam and power house for speed, while the work of the transmission line and Penstake pipeline will also start soon."

Project chief Subedi said that 4,220 meters of the entire underground structure, including the 6,425-meter main tunnel, had been completed by Tuesday. Dam in Dhawalagiri Rural Municipality-4 Singkosh Dobhan and power house in Ghimleti 9Kharpani0 are under construction.

mediabaaji add

Related News

Fluctuations in the price of the dollar and the euro: This is the exchange rate of foreign currencies on Wednesday

Kathmandu. Nepal Rastra Bank has determined the official exchange rate of foreign currencies for Wednesday. According to the latest information published by the Central Bank, today the buying rate of one US dollar has remained at 152 rupees 08 pai...

NMB Bank launches 'EV Auto Loan' at 0.5% for new electric vehicles

Kathmandu.  NMB Bank Limited has introduced loan facilities for new electric vehicles at a special interest rate starting from 0.5%, targeting the Naima Auto Expo. With the objective of promoting environment friendly transportation and sustai...

Completed 1 day training of National Life Insurance

Kathmandu. National Life Insurance Company has provided 1-day training to agents working in different branch offices of Bagmati and Madhesh provinces who have been selected based on the monthly plan brainstorming 2082 issued by the National Life I...

NMB Bank launches online loan tracking facility, customers can track their applications

Kathmandu. NMB Bank has launched an important digital facility for its customers. The bank has now provided the customer with the facility to track personal and small and medium loan application information in real time. The bank claims that with...

NEPSE rose by 9.93 points, 7.5 billion shares traded

Kathmandu. On the third trading day of the week, NEPSE index increased by 9.93 points to 2649.30 points. Today, when 1 crore 48 lakh shares of 334 companies were bought and sold, there was a turnover of more than 7 billion 12 crore rupees. Among t...

A decline of 27.64 points in NEPSE, limited to 5.15 billion

Kathmandu. On the third trading day of the week, the stock market NEPSE index fell by 27.64 points to 2595.24. In NEPSE, 134 lakh 3 thousand 898 shares of 322 companies were bought and sold on this day, and over 5.15 b...