Pokhara-Muglin road: 18 kilometers of the west section is black paper

Main News Image

Tanahun. The 18 km two-lane black road has been completed on the West Pokhara-Jamune section of the Pokhara-Muglin road. Thirty-eight kilometers of this stretch of road has been paved one-way for 37 kilometers so far. According to Sahansheela Kayastha, engineer of the section, the physical progress of the road has been 59.89 percent and the financial progress has been 47.80 percent. She said, '29.61 km two-way four lanes and 7.79 km one-way two lanes have been blacked out.'

In the current year, 14 km of black paper work has been done. Two culverts were constructed during the same period. 11 out of 12 bridges and 105 culverts in the western section have also been constructed. In urban areas, six-lane roads with 'service lanes' and four-lane roads will be built elsewhere. According to the project, there will be six lanes from Seti Bridge in Pokhara to Lower Gagangouda.

mediabaaji add

Related News

Repeal of the increase in health examination fees for those going abroad for employment

Kathmandu. The increase in the health examination fee of those going for foreign employment has been cancelled. Earlier, the test fee was increased from 6,500 to 9,500. Labour, Employment and Social Security Minister Rajendrasinh Bhandari canceled...

Senior Citizens Day is being celebrated with various programs

Kathmandu.  With the motto of 'Our Common Campaign: Respect and Respect for Senior Citizens', various programs are being organized today to celebrate Senior Citizen Day. This day is to be celebrated by organizing various programs to promote r...

The 1800 meter road has been lying idle for eight years

left The 1,800-meter Charlane road under construction at Khajura Bazar in Banke has been lying idle for the past eight years. Bikram Samvat 2074 Chait 29, a contract was signed with Gajurmukhi Construction Company Pvt....

Two laborers missing in Trishuli River, armed divers searching

Kathmandu. Two workers working at Super Trishuli Hydropower have gone missing in the Trishuli river. On Saturday afternoon, they went missing while bathing in the Trishuli river near the suspension bridge of Kuringhat located in Ichchakamana-4 of...

Labor agreement between Nepal and Saudi Arabia

Kathmandu. A bilateral labor agreement has been signed between Nepal and Saudi Arabia for ordinary workers. The signing was completed in Riyadh, Saudi Arabia, with the aim of promoting safe, orderly and dignified foreign employment of Nepali worke...

Celebrating the Undhauli festival of the Kirant community today

Kathmandu. On the day of Margashirsh Shukla Purnima today, the Kirant community is celebrating the Undhauli festival in honor of their ancestors and nature. The Yakkhas of the Kirat community celebrate the festival of...