Muglin -Malekhu road upgradation work started

Main News Image

Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.

According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.

According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.

This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.

mediabaaji add

Related News

Instructions to the Insurance Authority to submit a report within 10 days of the questions raised in the Finance Committee

Kathmandu. The Insurance Authority has been instructed to submit the questions raised in the Finance Committee with a report within 10 days. The chairman of the committee gave this instruction in today's discussion.

Insurance Authority Chair...

Trial of Tamghas-Burtibang 132 KV transmission line started

Kathmandu. The testing of the 132 kV double circuit transmission line constructed by the Nepal Electricity Authority from Gulmi headquarters Tamghas to Burtibang has been started from today. The line built under Burtibang-Paudiamrai-Tamghas-Sandhi...

The price of eggs increased from today

Kathmandu. Due to decrease in egg production and increase in demand, the price has been increased. Layers Poultry Farmers Association has fixed the new price based on the farm price to be implemented from May 1. According to the new rate, the farm...

The price of gold increased, how much per tola on Friday?

Kathmandu. The price of gold has increased in Nepali market today. Gold tola has increased by 3 thousand 400 rupees. According to the Nepal Gold and Silver Traders Federation, gold is being bought and sold at 296 thousand 100 rupees per tola today...

The panic of bananas in the Nepali market, with the shortage, a huge increase in prices

Kathmandu. There is currently an extreme shortage of bananas in the Nepali market. Such a situation has been created in the market after the businessmen themselves boycotted the bananas coming in illegally through the Indian border. Traders have b...

General decline in the price of gold, silver increased!

Kathmandu. In the Nepali market on Wednesday, the price of gold decreased, while the price of silver increased. Today, the price of gold has decreased by Rs 400 per tola. According to the Federation of Nepal Gold and Silver Traders, the price of p...