Muglin -Malekhu road upgradation work started

Main News Image

Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.

According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.

According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.

This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.

mediabaaji add

Related News

The request of the department to inform about the illegal trading of gas

Kathmandu. The Department of Commerce, Supply and Consumer Protection has requested all of you to call 1137 toll-free if you have any information or information regarding the illegal trading of LP gas for cooking due to the shortage in the interna...

Revenue collection of 21 lakh 10 thousand in one day in traffic action

Kathmandu. In the past 24 hours, two thousand 102 motorists have been prosecuted for violating traffic rules. From this, the revenue of Rs 21 lakh 10 thousand 514 has been deposited in the state treasury. According to the Kathmandu Valley Traffic...

What is the exchange rate of which foreign currency on Tuesday?

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the fixed exchange rate, the buying rate of one US dollar is 147 rupees 43 paisa and the selling rate is 148 rupees 3 paisa. The buying rate...

The tenth amendment of the National Bank Act 2058

Kathmandu. The Ministry of Finance has started the process of amending the existing legal structure related to Nepal Rastra Bank. The ministry has released the draft of the bill to amend the Nepal Rastra Bank Act, 2058 and has sought opinions and...

Discounted air fare for workers going to Gulf countries

Kathmandu. Nepal Airlines Corporation has implemented new fares with special discounts for Nepali workers going to Gulf countries. The corporation issued a statement today and decided to give a 10 percent special disco...

Share price increase of five companies, how much has increased?

Kathmandu. On the first day of the week, i.e. Sunday, the stock market fell by double digits. Today, the NEPSE index decreased by 26.51 points to 2649.52 points. Share prices of 45 companies from different sectors have...