Muglin -Malekhu road upgradation work started

Main News Image

Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.

According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.

According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.

This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.

mediabaaji add

Related News

From now on, when the airline's aircraft are diverted, they will land at Bhairahawa

Kathmandu. In the event that Nepal Airlines Corporation planes could not land at Tribhuvan International Airport due to various reasons, now Gautam Budh International Airport will be used. Spokesperson Anil Ghimire inf...

Dedicated trunk line dues dispute: Time given by authority expires today

Kathmandu. The last time given by Nepal Electricity Authority to pay the outstanding amount of dedicated and trunk line is ending today. According to the installment facility provided by the authority to the industrial...

An increase of 62.29 points in NEPSE, turnover of 4.57 billion

Kathmandu. On the second trading day of the week, the stock market NEPSE index increased by 62.29 points to 2571.34. 
On NEPSE, 92 lakh 43 thousand 723 shares of 314 companies were bought and sold on this day, with a turnover of 4.57 bil...

What is the exchange rate of which foreign currency on Friday?

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the determined exchange rate, the buying rate of one US dollar is 146 rupees 84 paisa and the selling rate is 147 rupees 44 paisa. Similarly,...

What is the foreign currency exchange rate today? see

Kathmandu.  Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the Rashtra Bank, the buying rate of one US dollar is 147 rupees 15 paise and the selling rate is 147 rupees 75 paise. 

Simi...

NEPSE decreased by 13.88 points today, turnover limited to 3.51 billion

Kathmandu. On the second trading day of the week, the NEPSE index decreased by 13.88 points to 2581.21. During the day, 91 lakh 67 thousand 359 shares of 332 companies were bought and sold, with a turnover of 3 billion 51 crore 59 lakh shares. Tod...