Muglin -Malekhu road upgradation work started
Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.
According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.
According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.
This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.
Express
Related News
The tea industry will be closed due to Indian barriers!
Elam. The tea industry in Suryodaya region of Elam is going to be closed after India tightens the Nepalese tea market. Suryodaya Orthodox Tea Producers Association Nepal, to which Tripanna Industry is affiliated, has announced the closure of the i...
Today's foreign currency exchange rate: what is the value of dollars, euros and pounds?
Kathmandu. Nepal Rastra Bank has announced the official exchange rate of foreign currencies for Wednesday. According to the new rate determined by the Central Bank, today the buying rate of one US dollar is Rs 151 16 paisa and the selling ra...
Nagadhunga is mostly deserted after the tunneling
Dhading Nagadhunga road, which is always smoky and chaotic with traffic jams, is mostly deserted this year even during Dashain. Nagadhunga-Sisnekhola tunnel, the main gateway to the federal capital Kathmandu from around 68 districts of the country...
Shangrila Development Bank declares 10 percent dividend
Kathmandu. The meeting of the board of directors of Sangrila Development Bank Limited held on the afternoon of 28th October has announced the dividend to the shareholders.
The meeting has announced that 5% bonus s...
Two white papers published by the government for the improvement of water and weather sector
Kathmandu. The government has released two white papers for strengthening the water and weather sector, making the flood warning system effective and disaster risk reduction. Hydrology and Water Resources Research Center and Department of Water an...
Double-digit growth in NEPSE, turnover limited to 3 billion 29 million
Kathmandu. On the second trading day of the week, the NEPSE index increased by 16.37 points to 2619.99. During the day, 78 lakh 4 thousand 45 shares of 325 companies were bought and sold, and 3 billion 294 million shar...