Muglin -Malekhu road upgradation work started

Main News Image

Kathmandu. The work of upgrading the Muglin-Malekhu road, which was only a normal work due to the rainy season, has started gaining intensity. After June, the road upgrading work slowed down. After the rain stopped and the festival was over, the work started to be intensified. According to Vijay Darai, engineer of the western section of the Muglin-Malekhu road under the Nagdhunga-Muglin road project, the work has been accelerated. The work on the access road to the bridge has been started. The access roads of four bridges are going to be constructed. Barrier work has been started on the bridge and other parts and drain work has also been started.

According to him, preparations have been made to start the black paper work in two to three days. Out of 38.86 kilometers of that section, eight kilometers of roads have been paved. Final preparations have been made for additional five kilometers of road blacking. According to Darai, the place where the final preparations have been made is about to be blacked out. Along with this, preparation work will be done for the black paper in other places. Among the other two bridges on that road section, one foundation of Charoodi Khol bridge has been laid. On the other hand, both the foundations of the Hoogdi river bridge have been prepared.

According to Darai, 35 percent of road upgrading has been completed so far. In this section, 2.2 km will be six-lane, which will be in Malekhu, Benighat and Muglin sections. The 7.2 km road will have four lanes. Stating that the four lanes will be in the areas of Danda, Kurintar, Fisling, Chumling, Mazhimtar, Charaudi and Vishaltar, Darai said that a three-lane 'climbing' route will be made in the uphill and downhill sections. According to him, the 'climbing' route will be 2.3 km and the rest of the road will be two lanes.

This road was contracted to be completed in three years on 15 January 2079. Under the Prithvi highway, Muglin-Nagdhunga section has been divided into three phases and bids have been invited. This falls under the third phase. It will expire on the 15th of January. Darai said that the process for extending the deadline has gone ahead. He said that the construction company will get an extension of a few months due to design modification etc.

mediabaaji add

Related News

Demand of the transport industry from the government to implement the tax exemption continuously and uniformly

Kathmandu. The National Federation of Nepal Transport Professionals has demanded from the government to implement the 60 percent tax discount that the transport sector is getting continuously and consistently. The Federation has sent a letter to t...

Nepal Rastra Bank is issuing 25 billion bonds today

Kathmandu. Nepal Rastra Bank today is going to issue 'Nepal Rastra Bank Bond 2084' with a one-year period worth 25 billion. The Monetary Management Department of the National Bank has issued a notification and said that it is going to issue the bo...

6 Public notice to terminate contract with builder

Kathmandu. The road division office under the Ministry of Physical Infrastructure and Transport, Roads Department, Sanfebagar, Achham, has warned of breaking the contract agreement with 6 builders who do not complete the work undertaken on time.

Double-digit decline in the stock market, turnover also decreased

Kathmandu. There was a double-digit decline in the stock market on Thursday. On this day, the NEPSE index decreased by 19.67 points and stood at 2601.92 points. As the NEPSE index fell, the turnover also decreased compared to Wednesday. On the pre...

65 crore worth of agricultural products in Parbat

the mountain In Parbat, which is becoming self-sufficient in food and vegetables, more than Rs. In the financial year 2081 and 2082, the volume of agricultural products produced by giving priority to the six main crops was traded. According to Par...

What is the exchange rate of which foreign currency on Thursday?

Kathmandu. Nepal Rastra Bank has determined the foreign currency exchange rate for Thursday. According to the fixed exchange rate, the buying rate of one US dollar is 144 rupees 83 paisa and the selling rate is 145 rupees 43 paisa. Similarly, the...