Construction of two hydropower projects of 84 megawatt capacity in Rahughat of Myagdi has been completed
Kathmandu. Tundi Power Company has simultaneously constructed two hydropower projects on the Rahughat River that flows through Raghuganga Rural Municipality of Myagdi. Ghuganga Rural Municipality-4, 7 and 8 Ward No. 4, 7 and 8 of the two projects of 84 MW capacity are connected to the electricity central system.
Pushpa Dangi, the company manager of Tundi Power, informed that after the testing of the project of the nature of 'Run of the River', the commercial production has started. "Chimkhola-Rahughat-Mangale with a capacity of 35.5 megawatts promoted by Tundi Power and Upper Rahughat hydropower project with a capacity of 48.5 megawatts as a 'cascade' have been put into operation", he said, "Chimkhola-Rahughat-Mangale has started commercial production since last July 20. It is in the stage of commercial production.
Manager Dangi said that the projects built during four years can be operated at full capacity according to the available water resources. According to him, the estimated cost of both projects is 13 billion. Resident engineer Prakash Timilsina said that the electricity generated from these projects is temporarily connected to the national system from the 'switchyard' of the Rahughat hydropower project in Raghuganga Rural Municipality-3 Tilkenichaur. According to him, 39 towers have been constructed from Chimkhola to Rahughat.
A 110-meter long, eight-meter high and 30-meter wide water-cooling pond has been constructed near the dam in Raghuganga Rural Municipality-8 Bandi of Chimkhola-Rahughat-Mangale. A 950-meter penstock pipeline has been installed to drop the water brought from the dam through a five-kilometer, 300-meter long tunnel to the power plant at Bagar in Raghuganga-7 Chimkhola. Engineer Timilsina informed that the height of the outlet of the tunnel from electricity is 360 meters.
Electricity has been generated from Chimkhola-Mangale-Rahughat by using water from Chimkhola-Mangale-Rahughat and Bagarkhola of Chimkhola. Raghuganga Rural Municipality-4 The tunnel of Upper Rahughat, where the power house is located at the foot of Dagnam, is 4,900 meters long. A 680 meter long penstock pipeline has been connected from the outlet to the power house.
Express
Related News
Petrol reduced by Rs 4 per litre
Kathmandu. Nepal Oil Corporation has reduced the prices of petrol, diesel, kerosene and jet fuel. According to the latest decision of the corporation, the price of petrol has been reduced by Rs 4 per liter and the price of diesel and kerosene has...
The price of petroleum products has decreased in Nepal
Kathmandu. Nepal Oil Corporation has reduced the price of petroleum products significantly. The board meeting of the corporation has decided to reduce the prices of petrol, diesel, kerosene, aviation fuel and LP gas for cooking. The new price will...
Foreign currency exchange rate announced: what is the price of dollar, euro and pound?
Kathmandu. Nepal Rastra Bank has determined the official exchange rate of foreign currency for today. According to the information released by the Central Bank, today the buying rate of one US dollar is 152 rupees 04 paisa and the selling rate is...
'Middleman's game' in banana prices, farmers' demand to fix minimum support price
Kathmandu. The Federation of Nepal Banana Producers has demanded the government to set the minimum support price for bananas. Through a press conference held on Tuesday, the federation said that such an arrangement is necessary to ensure fair pric...
The price of gold increased by 10,400 per tola in one day, how much did it reach?
Kathmandu. Today, the price of gold has increased by 10,400 rupees in one day. The price of gold reached 295 thousand one hundred on Wednesday, according to the Federation of Nepal Gold and Silver Traders. This price of gold is the most expensive...
Singti Hydro will issue 100 percent rights
Kathmandu. Singti Hydro Energy Limited is going to issue rights. The company has appointed Muktinath Capital Limited as the sales manager for the rights issue. Sudip Khadka, Managing Director on behalf of Singti Hydro Energy Limited and Kavindra D...