Adding date of commercial production of hydropower projects
Kathmandu. The Nepal Electricity Authority has prepared to add RCOD to the final date for starting commercial production of hydropower projects that have not been able to start commercial production due to various reasons despite the PPA.
The Authority has put forward a new RCOD management policy by classifying the hydropower projects into four different groups based on the on-site condition of the construction, the condition of fulfilling the obligations mentioned in the PPA and the overall physical progress.
The meeting of the Board of Directors of the Authority held on 32nd June has taken a formal decision to classify the projects that have PPA but have not yet been put into commercial operation into 'A', 'B', 'C' and 'D' groups.
Express
Related News
Genji Movement: Payment of over five billion claims for physical and other damages
Kathmandu. Out of the insurance claims for physical and other damages during the Zenji movement, Rs. 5.18 billion has been paid to the insured so far. The Nepal Insurance Authority issued a press release today and said that out of a total of 3,303...
Suryakund Hydro's IPO sale is open for general public from today
Kathmandu. Suryakunda Hydro Electric has opened the IPO sale for the general public from 18th January today. In the second phase, the company is going to issue a total of 572 thousand 431 shares of Rs 100 for general investors.
In this...
Prabhu Bank CEO and Two Senior Executives Arrested in Banking Fraud Probe
KATHMANDU — Nepal Police’s Central Investigation Bureau (CIB) on Sunday arrested Prabhu Bank Chief Executive Officer Ashok Sherchan, along with Deputy CEO Mani Ram Pokharel and Chief Credit Officer Rivas Sh...
What is the exchange rate of which foreign currency on Thursday?
Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to Rashtra Bank, the buying rate of one US dollar has been fixed at 145 rupees 22 paisa and the selling rate is 145 rupees 82 paisa. Similarly,...
The government gave the permission, the industrialists increased the price of gas
Kathmandu. Industrialists have increased the price of cooking gas. The industrialists have increased the price of gas by 150 rupees and 18 paise per cylinder on the pretext of increasing the cost of transportation due to the blockage of Prithvi Hi...
IPO distribution of Ridge Energy completed, 1 lakh 18 thousand people got shares
Kathmandu. Ridge Line Energy Limited has completed the IPO process issued to the general public. Sales manager Prabhu Capital completed the allotment this morning. IPO of the company 118 thousand 26 people have acquired 11 lakh 80 thousand 260 sha...