8 billion spent on the north-south road, black paper target up to Korla
Kathmandu. As part of the north-south trade route expansion project, Rs. The project has spent 82 percent of the budget while the proposed cost estimate of the project is Rs 10.57 billion till FY 2081-82.
Under the Korla road of national pride connecting India and China, a 202 km road track has been opened from Maludhunga in the mountain to Nepal-China Korlana. According to the decision of the Council of Ministers on November 12, 2073, Kaligand Corridor 9Beni-Jomsam-Korla road was established as a separate project. Under which the project has been continuously upgrading the roads in Parbat, Myagdi and Mustang sections since 2073 and 74. The last revised completion period of the project has been proposed for the year 2082 and 2083. But since the road up to Korlanaka needs to be paved, it is certain that the completed period will be revised again.
Under this Kaligandaki Corridor road project, the target is to open 202 km of road tracks, 97 km of road gravel, 150 km of tarmac and 19 bridges. According to the target, by the year 2081 and 2082, the project has opened 202 kilometers of road tracks, 94 kilometers of road gravel, 88 kilometers of black paper and construction of 14 bridges have been completed, project chief Tejashwi Sharma has informed.
For Korla road, through the project, 3 km of gravel and 10 km of Kagbeni-Chusang will have to be blacked on 27 km of the road and a new contract will have to be issued for the rest. Under this project, if the 9 Kagbeni-Korla road section is also covered with black, the total cost estimate of the project may be more than 15 billion, according to the head of the project Sharma. According to the head of the project, the goal is to upgrade the road and blacken the entire 202 km double lane of the Korla road section and build the necessary bridge.
Express
Related News
The price of gold increased, how much per tola on Sunday?
Kathmandu. The price of gold has increased in Nepali market today. Gold rose by 3,500 rupees per tola in one day. According to the Nepal Gold and Silver Traders Federation, gold is being traded at Rs 3 lakh 16 thousand 900 per tola today. On the o...
FPO Allotment of Vijay Laguvitta
Kathmandu. The FPO of Vijay Laguvitta Financial Institution has been distributed today on 6th of January. The FPO of Vijay Laguvitta was distributed this morning at the office of securities sales manager NMB Capital. After the merger of Savik's ne...
NEPSE rose, the index to 2,597 points as share prices of 121 companies increased
Kathmandu. On Thursday, the last trading day of the current financial year, the Nepal Stock Exchange NEPSE index has closed with an increase of normal points. The market, which has been fluctuating throughout the day, improved at the end of tradin...
What is the exchange rate of which foreign currency on Monday?
Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the fixed rate, the buying rate of one US dollar is 144 rupees 02 paisa and the selling rate is 144 rupees 62 paisa.
Similarly, t...
Unseasonal rain in Morang has reduced paddy production, farmers are worried
Morang. In terms of rice production, Morang district, which is considered to be the best in the country, has seen a decrease in rice production this year due to unseasonal rains. Compared to last year, the production o...
Farmers line up overnight to sell paddy, rush to government procurement centre
Kailali. Swaroop Chaudhary from Ghodaghodi Municipality-3 here went to Bhajani to sell paddy early on Saturday morning. After the government started buying paddy by fixing the support price of paddy, the sub-centre of the Food Management and...