8 billion spent on the north-south road, black paper target up to Korla
Kathmandu. As part of the north-south trade route expansion project, Rs. The project has spent 82 percent of the budget while the proposed cost estimate of the project is Rs 10.57 billion till FY 2081-82.
Under the Korla road of national pride connecting India and China, a 202 km road track has been opened from Maludhunga in the mountain to Nepal-China Korlana. According to the decision of the Council of Ministers on November 12, 2073, Kaligand Corridor 9Beni-Jomsam-Korla road was established as a separate project. Under which the project has been continuously upgrading the roads in Parbat, Myagdi and Mustang sections since 2073 and 74. The last revised completion period of the project has been proposed for the year 2082 and 2083. But since the road up to Korlanaka needs to be paved, it is certain that the completed period will be revised again.
Under this Kaligandaki Corridor road project, the target is to open 202 km of road tracks, 97 km of road gravel, 150 km of tarmac and 19 bridges. According to the target, by the year 2081 and 2082, the project has opened 202 kilometers of road tracks, 94 kilometers of road gravel, 88 kilometers of black paper and construction of 14 bridges have been completed, project chief Tejashwi Sharma has informed.
For Korla road, through the project, 3 km of gravel and 10 km of Kagbeni-Chusang will have to be blacked on 27 km of the road and a new contract will have to be issued for the rest. Under this project, if the 9 Kagbeni-Korla road section is also covered with black, the total cost estimate of the project may be more than 15 billion, according to the head of the project Sharma. According to the head of the project, the goal is to upgrade the road and blacken the entire 202 km double lane of the Korla road section and build the necessary bridge.
Express
Related News
Revenue collection of 21 lakh 10 thousand in one day in traffic action
Kathmandu. In the past 24 hours, two thousand 102 motorists have been prosecuted for violating traffic rules. From this, the revenue of Rs 21 lakh 10 thousand 514 has been deposited in the state treasury. According to the Kathmandu Valley Traffic...
What is the foreign exchange rate on Saturday?
Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. Fixed exchange rate The buying rate of one US dollar is 148 rupees 07 paisa and the selling rate is 148 rupees 67 paisa. Similarly, the buying rate of the...
Gas subsidy being scrapped
Kathmandu. The government has released Energy Consumption Growth and Export Strategy, 2083 with a plan to cancel the subsidy on LP gas for cooking till the financial year 2092 and 93 and provide subsidy on electric stoves. The strategy, published...
Gold price increased by 1400 rupees per tola, silver set a new record
Kathmandu. The price of gold and silver has also increased in the Nepalese market on Monday. Today, the price of gold has increased by 1 thousand 400 rupees. According to the Federation of Nepal Gold and Silver Busines...
Trial of Tamghas-Burtibang 132 KV transmission line started
Kathmandu. The testing of the 132 kV double circuit transmission line constructed by the Nepal Electricity Authority from Gulmi headquarters Tamghas to Burtibang has been started from today. The line built under Burtibang-Paudiamrai-Tamghas-Sandhi...
Hotel View Bhrikuti has announced a special offer for the English New Year
Lalitpur. Hotel View Bhrikuti has announced a special festive offer for guests on the occasion of Christmas and English New Year 2026. The hotel management said that the offer will be applicable from December 24, 2025 to January 1, 2026.