The 12-year blockage of Dhalkebar-Hetaunda 400 KV transmission line has been removed
Kathmandu F. The government has removed the main obstacle to the construction of Dhalkebar Hetaunda 400 KV high voltage transmission line, which has been stalled for various technical and legal reasons for the past 12 years. With the important decision of the cabinet meeting held on Wednesday, the way to use the forest area in the Makwanpur section of the project, which has been stuck for a long time, has been opened.
The Council of Ministers has given approval to the Nepal Electricity Authority to use 2=2 hectares of national forest land under the Ratomate Community Forest User Group at Hetounda 15 of Makwanpur and the Saraswati Community Forest User Group at Bakia 2 in accordance with Section 42 1 of the Forest Act, 2076 for the project. In addition to this, the government has also granted permission to cut 1,292 trees of various species in the said forest area.
Express
Related News
2 million shares of Bhujung Hydropower IPO coming
Kathmandu. Nepal Securities Board Sebon has given permission to Bhujung Hydropower Limited to issue an initial public issue IPO to the general public. Sebon has given approval to the company to issue 2 million shares w...
More liquidity in banking system, Rashtra Bank pulling 50 billion today
Kathmandu. Nepal Rastra Bank is going to withdraw 50 billion rupees from the banking system today, January 28th. To manage excess liquidity, the central bank is using deposit collection tools to withdraw money from the banking system.
...
Gold decreased by 10,000 rupees per tola in one day, how much per tola?
Kathmandu. The price of gold in the Nepali market has fallen drastically. Gold tola decreased by 10 thousand 100 rupees. According to the Nepal Gold and Silver Traders Federation, gold is being traded at 291,800 rupees per tola today.
On the...
5 lakh more income in one year from flower farming
Walling. Tulsiram Bhandari of Chapakot Municipality-1 Chowghera in Syangja has been earning five lakhs more in a year from commercial flower farming. He, who is also a former teacher, has been cultivating flowers targeting Dasain and Tihar.
<...125 contracts stopped due to fuel price hike
Chitwan. 125 contract works run by Infrastructure Development Office Chitwan have come to a halt. Due to the rising cost of essential items including fuel, it has become impossible to work on these contracts. According to the head of the office, B...
1 Crore more income from selling Bajura's organic apples
Bajura. An income of more than 1 crore has been earned from the sale of organic apples produced in Bajura. The apple farmers here have earned an income of 15 million rupees by selling apples. The amount was collected from the sale of apples produc...