Fourth extension of Pokhara-Muglin road project
Kaski. Pokhara-Muglin road upgrading project has been extended for the fourth time. After the deadline extended for the third time has passed, the project has been given the final deadline till the 10th of November.
According to Krishna Bahadur Kumbar, Project Chief of Muglin-Pokhara Road Project, West Section, the previously extended deadline was till June 15th, but the time was extended again as the construction could not be completed. He claimed that the work will be completed within the specified period, mentioning that the added time is now final.
The 38.71 km road from Jamune in Tanahun to Setipul in Pokhara under the Prithviraj Marg upgradation project started five years ago with the loan support of Asian Development Bank ADB is in the western section. In this area, a six-lane road is being constructed in the market and a four-lane road in the hilly areas. According to the project, 82.37 percent physical progress has been made so far.
Express
Related News
New payment gateway launched by NMB Bank for Digital Nepal
Kathmandu. NMB Bank, in collaboration with Nepal Clearing House Limited, has launched a card-based online payment gateway to simplify and secure digital transactions across the country. This new service will greatly he...
Inflation reached 5.96 percent for the general public
Kathmandu. In the first month of the current fiscal year 2083/84, in July, the annual point consumer inflation of Nepal has reached 5.96 percent. According to the economic and financial situation statistics released by the Nepal Rastra Bank in the...
Dollar, Euro and Saudi Riyal fluctuations: see what is the exchange rate of which currency today?
Kathmandu. Nepal Rastra Bank has announced the official exchange rate of foreign currency for today. According to the Central Bank, today the buying rate of one US dollar is 153 rupees 28 paisa and the selling rate is 153 rupees 88 paisa.
Si...