Fourth extension of Pokhara-Muglin road project
Kaski. Pokhara-Muglin road upgrading project has been extended for the fourth time. After the deadline extended for the third time has passed, the project has been given the final deadline till the 10th of November.
According to Krishna Bahadur Kumbar, Project Chief of Muglin-Pokhara Road Project, West Section, the previously extended deadline was till June 15th, but the time was extended again as the construction could not be completed. He claimed that the work will be completed within the specified period, mentioning that the added time is now final.
The 38.71 km road from Jamune in Tanahun to Setipul in Pokhara under the Prithviraj Marg upgradation project started five years ago with the loan support of Asian Development Bank ADB is in the western section. In this area, a six-lane road is being constructed in the market and a four-lane road in the hilly areas. According to the project, 82.37 percent physical progress has been made so far.
Express
Related News
This week, NEPSE increased by normal numbers, which day's business is how much?
Kathmandu. This week, the NEPSE index increased by 0.89 points and reached 2641.43 points. NEPSE, which closed at 2640.54 points last week, increased by 0.89 points to 2641.43 points this week. The market was open for only three trading days this...
The government will give 25,000 per family displaced from the river banks of the valley
Kathmandu. The government has decided to provide a lump sum of Rs 25,000 as a relief to the families who will be displaced after the removal of hazardous settlements on the banks of various rivers in Kathmandu Valley. The cabinet meeting held at S...
Three billion worth of electric vehicles entered in 9 months through the Birganj border crossing
Parsa. In the nine months of the current financial year, electric vehicles worth 2.98 billion rupees have been imported through the Birganj route. Compared to the same period of the last financial year, electric vehicles have been imported by 102...
11 km Nagadhunga-Malekhu section under Prithvi Highway is blacked out
Chitwan. Under Prithvi Highway, 11 km Nagdhunga Malekhu section has been blacked out. Last year eight kilometers were blacked, this year three more kilometers were blacked. According to Vijay Darai, Engineer of Nagadhunga Muglin Road Project, unde...
What is the exchange rate of foreign currency on Saturday?
Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to the National Bank, the buying rate of one US dollar has been fixed at 141 rupees 70 paisa and the selling rate h...
Egg price increased: Rs. 25 per egg for consumers, farmers still at a loss
Chitwan. As the production of eggs decreases with the summer season, the price has increased. Nepal Layers Poultry Association has increased the support price of eggs. According to the association, a farm rate of Rs 515 per crate of 930 eggs for l...