Construction of 27 km road of Naubise-Malekhu section completed

Main News Image

Kathmandu. Under the Nagadhunga-Mugling road expansion project, the construction work of Naubise-Malekhu section has gained momentum. In this second section, which has a total length of 43 km, a total of 27 km of road construction has been completed with 25 km of asphalt and 2 km of sloping rigid pavement.

According to Keshav Ojha, head of planning of Nagadhunga-Mugling road project eastern section, the overall physical progress of this section has reached 60 percent. Although the project aims to achieve 75 percent physical progress in the current financial year, due to the lack of bitumen in the international market, some obstacles were created in achieving the goal. He informed that although there was a problem in the supply of bitumen due to the tension in the Middle East, the supply has been eased after the facilitation of the Ministry of Infrastructure Development and the work has resumed speed.

mediabaaji add

Related News

New code implemented for construction of earthquake resistant buildings

Kathmandu. The government has revised and implemented the National Building Code for the construction of earthquake resistant buildings. Provisions in the old code are impractical and inconsistent with international st...

Chhath festival preparations begin in Mithila

Surlahi. With the end of Tihar, Mithilanchal is now full of Chhath festival. The villages and towns here have turned festive to welcome Chhath, which is considered one of the major religious festivals of the country. O...

Preparing to finalize the agreement between the government and the protestors

Kathmandu. Prime Minister Sushila Karki discussed with the leading representatives of Gen-G movement today. The issue of finalizing the draft agreement between the government and the protestors was discussed. Genji rep...

Permission for construction of three transmission lines

Kathmandu. The government has granted permission for the construction of three transmission lines so far in the current financial year. The Electricity Development Department under the Ministry of Energy, Water Resources and Irrigation has granted...

One missing, one injured in Gharkhola hydroelectric power plant due to dry landslide in Myagdi

Myagdi. One worker went missing and another was injured when a landslide occurred at the 14 MW Gharkhola hydroelectric power plant located in Pokhrebgar, Annapurna rural municipality 6 of Myagdi this morning.

According to District Police Off...

Heavy snowfall accompanied by rain in Mustang, Humla and Bajura

Mustang. There has been heavy snowfall in various parts of the district since Tuesday night. The hills here are completely covered. It has also rained in most places. Kagbeni-Korla road has been blocked due to heavy snowfall. More than two feet of...