Authority constructing new Butwal Lamhi transmission line
Kathmandu. The Nepal Electricity Authority is going to construct a new Butwal Lamahi power transmission line with a capacity of 400 KV. The total length of 161 km transmission line is intended to transmit the electricity of eastern Nepal to the west and to construct the transmission line for the electricity transmission of the power projects built in the Gandaki Corridor.
The authority is going to implement the project in Nawalparasi, Rupandehi, Palpa, Kapilvastu, Arghakhanchi and Dang districts of Lumbini province. For the preparation of Environmental Study 9 Preliminary Environmental Test 0 report in the affected area of the transmission line, it is requested to publish public notice and give necessary suggestions and advice.
46 meters of the transmission line with a total capacity of 400 kV has been assigned. Jurisdiction is defined as 23 meters to the right and 23 meters to the left of the center of the transmission line.
There will be a total of 450 towers on the transmission line. Similarly, a substation of 400 (220) 132 (33) 11 KV capacity will be constructed in Rihar located in Ward No. 9 of Lamhi Municipality of Dang.
It is also mentioned in the notification that the authority is going to prepare the environmental study report and what kind of impact it will have on the natural physical system, biological system, social system, cultural and economic system of the area.
Express
Related News
The number of candidates opening accounts in banks and financial institutions is increasing
Kathmandu. After the Election Commission mandated that election expenses should be paid through bank and financial institution accounts, candidates opened accounts in a hurry. The Commission has arranged for political parties and candidates to ope...
Public debt reached 58 trillion
Kathmandu. The share of public debt in GDP has reached 47.13 percent. As the government took 28 trillion 78 billion rupees in public debt till the end of February of the current financial year, its ratio to GDP has increased. According to the Publ...
Pokhara-Muglin road: The deadline for the western section has been extended for the third time
Kathmandu. Under the Prithviraj Highway, Pokhara-Muglin Road Expansion and Upgrading Project has been extended for the third time for the western section. This highway, which connects the tourist capital Pokhara to the federal capital Kathmandu, i...
Crude oil prices fall on signs of opening of Hormuz, new record in US stock market
Kathmandu. The diplomatic talks between Iran and Oman regarding the resumption of the safe passage of commercial ships through the Strait of Hormuz have indicated that they are progressing in a positive direction.
After the representatives o...
What is the former king in India doing in the discussion for more than a week on the security of the governor?
Kathmandu. Former King Gyanendra Shah is currently in India. The former king, who is in Siliguri, India, reached Siliguri via Damak on 2nd of January. There is no indication that Purvaraja will return in 1-2 days. It is not clear how long the form...
What is the exchange rate of which foreign currency on Thursday?
Kathmandu. Nepal Rastra Bank has determined the foreign currency exchange rate for Thursday. According to the fixed exchange rate, the buying rate of one US dollar is 144 rupees 83 paisa and the selling rate is 145 rupees 43 paisa. Similarly, the...