Authority constructing new Butwal Lamhi transmission line
Kathmandu. The Nepal Electricity Authority is going to construct a new Butwal Lamahi power transmission line with a capacity of 400 KV. The total length of 161 km transmission line is intended to transmit the electricity of eastern Nepal to the west and to construct the transmission line for the electricity transmission of the power projects built in the Gandaki Corridor.
The authority is going to implement the project in Nawalparasi, Rupandehi, Palpa, Kapilvastu, Arghakhanchi and Dang districts of Lumbini province. For the preparation of Environmental Study 9 Preliminary Environmental Test 0 report in the affected area of the transmission line, it is requested to publish public notice and give necessary suggestions and advice.
46 meters of the transmission line with a total capacity of 400 kV has been assigned. Jurisdiction is defined as 23 meters to the right and 23 meters to the left of the center of the transmission line.
There will be a total of 450 towers on the transmission line. Similarly, a substation of 400 (220) 132 (33) 11 KV capacity will be constructed in Rihar located in Ward No. 9 of Lamhi Municipality of Dang.
It is also mentioned in the notification that the authority is going to prepare the environmental study report and what kind of impact it will have on the natural physical system, biological system, social system, cultural and economic system of the area.
Express
Related News
The amount of contribution to the social security fund reached one billion
Kathmandu. The amount of contribution to the social security fund, which the government has started to bring the citizens under the scope of social security, has reached nearly one billion. According to the fund, so fa...
Today, NEPSE closed down by 13.52 points, trading at 5.23 billion
Kathmandu. On the fourth trading day of the week, NEPSE index decreased by 13.52 points and remained at the point of 2631.17. During the day, 1873 thousand 372 shares of 332 companies were bought and sold, with a turno...
Preparing to operate traffic through the reconstructed BP highway during rainy season
Kavrepalanchok. BP Highway, which has been damaged by repeated floods and landslides, is currently undergoing permanent reconstruction. Divisional Road Office Bhaktapur said that the permanent reconstruction work started at three places of the dam...
Authority reviewing electricity tariffs: Preparation to reduce tariffs and increase domestic consumption
Kathmandu. Nepal Electricity Authority has started the review process with the aim of making the electricity tariff structure timely. With the goal of maximum utilization of electricity, expansion of internal consumption and development of consume...
Purchase of paddy at support price by cooperative in Bardia, relief to farmers
Bardia. The government had fixed the minimum support price of rice at the time to provide a fair price of rice to the farmers. Although the minimum support price of paddy was fixed, the farmers were not able to get the...
The market is full of people for Janaipurnima!
Kathmandu. Aiming at Janaipurnima, which falls on 12th of August, jaai are kept for sale in the market. For Janaipurnima, various shapes and types of janai are decorated in shops.