ADB Project’s Rs 420 Million Budget Under Scrutiny, Consultant Selection Sparks Controversy
Kathmandu — The consultant and service provider selection process under the Rural Connectivity Improvement Project, implemented through the Department of Local Infrastructure Development with support from the Asian Development Bank, has come under controversy.
Stakeholders have raised serious questions over the transparency of the consultant selection process, alleging that the evaluation criteria prepared for training and capacity development programs could benefit only a limited number of institutions.
The project has a total budget of Rs 420 million and is expected to benefit around 5,909 people. Approximately Rs 240 million has been allocated for capacity development services, while around Rs 180 million has been allocated for skills development training.
Stakeholders have demanded that the ongoing Expression of Interest process be cancelled and restarted using transparent, objective and competitive criteria. A delegation representing the concerned stakeholders submitted a memorandum to the Director General of the Department of Local Infrastructure Development, Ashok Kumar Shah, raising concerns over the evaluation process.
One of the major concerns is related to the scoring system for joint venture partners. According to the stakeholders, the lead partner is allocated 20 points, while the JV partner receives only five points. They argue that JV partners also carry technical and managerial responsibilities and therefore their experience should receive appropriate weight in the evaluation.
Questions have also been raised about the definition of similar project experience and the criteria used to evaluate experience in capacity development programs. Stakeholders say unclear evaluation standards could prevent qualified organizations from receiving equal opportunities.
The stakeholders have further alleged that internal manipulation may have taken place during the consultant shortlisting process. They have claimed that certain officials involved in the project attempted to favor a limited number of consultants. However, the officials named in the allegations have not yet issued a detailed public response.
The stakeholders have called for the procurement process to be conducted in accordance with ADB procurement principles and international standards. They have emphasized that a project involving a large amount of public and development funding must maintain transparency at every stage, from the submission of expressions of interest to the technical and financial evaluation of proposals.
The matter has also been brought to the attention of the Office of the Prime Minister and Council of Ministers, ADB’s Nepal Office, the Commission for the Investigation of Abuse of Authority, the National Vigilance Center and the Public Procurement Monitoring Office.
Stakeholders have urged the concerned authorities to investigate the allegations, review the disputed evaluation criteria and take action if any irregularities are established.
They have also demanded that all qualified consulting firms be provided with equal opportunities through a fair and competitive selection process.
The controversy surrounding the Rs 420 million ADB-supported project has raised broader concerns about transparency, accountability and the effective use of development funds. Stakeholders have urged the government and concerned agencies to address the concerns promptly so that the project’s objectives are not affected.
Express
Related News
Exchange rate: The price of dollar, euro and pound has increased, which currency is being bought and sold in how much?
Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for Sunday. According to the fixed exchange rate, the buying rate of one US dollar is 151 rupees 56 paisa and the selling rate is 152 rupees 16 paisa.
Similarl...
The budget is meant to feed the ambitious and wealthy, the target is not met: Former Finance Minister Mahat
Kathmandu. Former finance minister and Nepali Congress leader Dr. Prakasharan Mahat has commented that the budget for the next financial year 2083-84 brought by the government is very ambitious and it has taken a policy to feed the rich class rath...
Nabil Bank won the Trishuli hydropower case in the Chinese court
Kathmandu. Nabil Bank Limited has succeeded in the case related to the counter guarantee of the Trishuli Hydropower Company Limited project in the Chinese court. Nabil Bank said that after the Chongqing Higher People's Court of China ruled in favo...
Fourth extension of Pokhara-Muglin road project
Kaski. Pokhara-Muglin road upgrading project has been extended for the fourth time. After the deadline extended for the third time has passed, the project has been given the final deadline till the 10th of November.
According to Krishna Baha...
The corporation claims that 25 bullets are being imported more than the demand for cooking gas
Kathmandu. Nepal Oil Corporation Executive Director Chandika Prasad Bhatt clarified that there is no shortage of cooking gas in the market. He said that the rumor that there is going to be shortage of gas in recent times is baseless and asked the...
9.23 points increase in NEPSE, turnover above 9 billion
Kathmandu. On the second trading day of the week, the NEPSE index increased by 9.23 points to 2714.61. During the day, 10.9 million 75 thousand 756 shares of 332 companies were bought and sold, and 9 billion 73.39 million shares were traded. Today...