125 contracts stopped due to fuel price hike

Main News Image

Chitwan. 125 contract works run by Infrastructure Development Office Chitwan have come to a halt. Due to the rising cost of essential items including fuel, it has become impossible to work on these contracts. According to the head of the office, Birendra Kumar Chaudhary, there are 267 projects in this office, and 217 of them are currently under contract. Out of them, 125 projects have come to a standstill, he said. According to him, the infrastructure development work has stopped due to the increase in fuel prices and the problem of shortage of vitamin 0 compared to the time when the contract was signed.

Chief Chaudhary said, "Construction professionals have submitted a letter to the office demanding a process to stop the 'construction holiday' projects of a nature that can be stopped immediately." He said that after the increase in the price of fuel, infrastructure construction is being affected due to the increase in prices in all sectors. 

Although 50 projects are to be done by the consumer committee from this office, the work of those projects has not been completed. He said that the office is currently constructing 19 bridges and roads are being constructed under other projects.

mediabaaji add

Related News

12 lakh 82 thousand shares of Himalayan Bank for sale

Kathmandu. More than 12 lakh 82 thousand shares of Himalayan Bank have been put up for sale. 12 lakh 82 thousand 588 shares of the founder group of the bank have been put up for sale. At present, only the existing founder shareholders of the bank...

In the first quarter, the expenditure of Kathmandu Metropolitan City was 12.94 percent

Kathmandu. In the first quarter of the current financial year, the total expenditure of Kathmandu Metropolitan City has reached 12.94 percent. Of the allocated 25 billion 11 crore 43 lakh 41 thousand rupees, 3 billion...

Construction of Kohalpur-Surkhet 132 KV transmission line has been completed

Kathmandu. Nepal Electricity Authority has completed the construction of Kohalpur-Surkhet 132 KV transmission line. The construction of the Kohalpur-Surkhet section has been completed under the Kohalpur-Surkhet-Dailekh 132 KV transmission line pro...

A ship carrying 30,000 metric tons of urea arrived at Calcutta port

Kathmandu. A third ship carrying 30,000 metric tons of urea fertilizer has arrived at Calcutta port in India with the aim of providing timely chemical fertilizers to the farmers of Nepal. According to the Ministry of Agriculture and Livestock Deve...

Are you exchanging foreign currency? Find out today's foreign currency exchange rates

Kathmandu. Nepal Rastra Bank has determined the exchange rate of foreign currency for today. According to Rashtra Bank, the buying rate of one US dollar has been fixed at 141 rupees 75 paisa and the selling rate is 142...

4.28 points decline in NEPSE, turnover of 4 billion 71 crores

Kathmandu. On the second trading day of the week, the NEPSE index decreased by 4.28 points to 2645.24. During the day, 18,60,828 shares of 325 companies were bought and sold, and over 4.71 billion shares were traded. T...